EDITABLE WORK DOCUMENT

Bid Questions, Official Answers and Proposal Changes

Record unclear wording, the official answer and where you changed the proposal or price sheet. Examples cover confirmed scope, an unanswered question and a changed rehearsal date.

WHAT THIS TEMPLATE HELPS YOU PREPARE

A record showing where official answers were applied to prices, staffing and schedules.

File formats
English XLSX · CSV (UTF-8)
Version
2.0
Editorial review
24 Oct 2026
Use this for
Use when tender documents conflict or do not make the required work clear. Follow the official question channel and deadline in the notice.

When to use it

Use when tender documents conflict or do not make the required work clear. Follow the official question channel and deadline in the notice.

Notices and answers in the examples are fictional. A telephone conversation is not automatically a formal amendment. Foreign procurement deadlines do not apply to Korean tenders.

Start with the guide: Event Tender Questions and Answers and Conditions Application

Fill in the template step by step

When to use it

Before the query cutoff and at the final proposal check.

What to have ready

  • Notice, scope and amendment originals
  • Page references and detailed proposal pricing
  • Official query channel, deadline and answers
  1. Record the unclear wording and page. Explain how different interpretations would change the cost or schedule.

  2. Send one issue per question through the designated channel and keep the receipt.

  3. Check which bidders the official answer applies to and which document version is current.

  4. Compare the changes in the proposal, price sheet and staffing plan. Leave unanswered items for the bid lead to decide whether submission can proceed.

Worked example

Fictional example, not an actual event or supplier record

Eight columns · scroll horizontally to view the complete worked example.

Bid Questions, Official Answers and Proposal Changes — fictional worked example
Question ID and notice numberDocument, page and wording to clarifyQuestion and possible interpretationsEffect on price and scheduleOfficial question channel and deadlineAnswer and bidders it applies toChanged document version and pageUnanswered items and action required
Q-01 / Fictional notice EVT-2026-11Scope v1 p.8 / “all video equipment”Does this include 3 cameras and recorded-file delivery?Add 1 camera; exclude editing following the answer. Fictional increase: KRW 550,000.Designated query portal / cutoff 2026-11-02 15:00Official A-01, 11-03: all bidders must include 3 cameras and raw files, with editing excluded.Technical v3 p.16 / price VIDEO-03 +KRW 550,000Proposal lead checked matching quantities in technical and price documents at 11-04 10:00.
Q-02 / EVT-2026-11Scope p.12 strike until 22:00 / venue p.4 vehicle access ends 21:00Who approves and pays for vehicle access after 21:00?Late access changes vehicle and crew planPortal submitted 11-02 14:10 / receipt Q-02No official answer by 11-03 17:00. Keep phone advice as a reference note only.Conditional plan recorded in proposal v3 p.24. Keep price ALT-02 on hold separately.Bid lead: check for an answer at 11-04 09:00 and decide whether to submit on these conditions.
Q-03 / EVT-2026-11Amended notice v2 p.2 / rehearsal date changeDoes the move from 11-10 to 11-11 apply to all suppliers?Change schedules for 6 operations staff and 4 technical staff, and the venue handover date.Download formal amendment / 11-03 16:00Amendment A-03 moves all rehearsals to 11-11.Update SCH-v4 and staffing commitment STAFF-v3. Withdraw obsolete versions.PM: receipts from 3 suppliers confirmed at 11-04 11:30; final submission pack v4 confirmed.

Blank template preview

This preview shows a few rows. The downloaded file contains 24 prepared rows.

Eight columns · scroll horizontally to view the complete blank worksheet.

Bid Questions, Official Answers and Proposal Changes — blank worksheet
Question ID and notice numberDocument, page and wording to clarifyQuestion and possible interpretationsEffect on price and scheduleOfficial question channel and deadlineAnswer and bidders it applies toChanged document version and pageUnanswered items and action required
————————
————————
————————

Check your completed template

  • Every official answer identifies where it was applied in the proposal or price sheet.
  • Unanswered questions remain visible separately from the decision to submit on stated assumptions.

What to pass to the next person

The proposal PM collects technical and commercial checks before handing the final pack to the submission owner.

Check before using this template

This register does not establish eligibility, legal compliance or binding contract interpretation. The specific procurement procedure takes precedence.