Loading-bay and Shared-route Schedule

Record vehicle arrival separately from the time each team uses the loading bay and shared routes. Resolve clashes with the venue and suppliers, checking the effect on installation and rehearsal.

WHAT THIS TEMPLATE HELPS YOU PREPARE

A supplier load-in schedule showing shared-area bookings and how clashes were resolved.

File formats
English XLSX · CSV (UTF-8)
Version
2.0
Editorial review
24 Oct 2026
Use this for
Complete before confirming vehicle dispatch. If a vehicle is delayed, recheck the effect on the teams scheduled after it.

When to use it

Complete before confirming vehicle dispatch. If a vehicle is delayed, recheck the effect on the teams scheduled after it.

Example times are fictional bookings, not standard unloading durations. Verify venue reservations, handling, traffic and work-safety conditions separately.

Start with the guide: Venue Load-in Scheduling and Shared-area Coordination

Fill in the template step by step

When to use it

Before booking load-in or dispatching vehicles, and whenever arrivals are delayed.

What to have ready

  • Venue load-in bookings
  • Each supplier’s vehicle and equipment list
  • Plan showing loading-bay and shared-route IDs
  • Work that must finish before installation and rehearsal can start
  1. Enter vehicle arrival and departure separately from loading-bay and route use.

  2. Mark any overlap where suppliers need the same bay or route.

  3. Ask suppliers whether a changed slot delays installation or rehearsal.

  4. Once the venue and suppliers agree, send the same schedule to drivers and onsite control.

Worked example

Fictional example, not an actual event or supplier record

Eight columns · scroll horizontally to view the complete worked example.

Loading-bay and Shared-route Schedule — fictional worked example
Supplier and task IDVehicle arrival and departureLoading bay and booking timesShared route and use timesInstallation position, sequence and start conditionsOverlapping times and changesVenue and supplier contactsApproved schedule version and change time
Video V012026-11-09 08:00–08:40D2 08:05–08:25C1 08:15–08:35Stage left. Begin installation after floor protection is complete.Approved to go first. Confirm the vehicle leaves after unloading.Venue Lee; video ParkLOAD-v2 / approved 2026-11-08 15:00
Audio A012026-11-09 08:20–09:00D2 08:20–08:40C1 08:25–08:45FOH. Begin installation after the cable route is prepared.Clashes with video: D2 for five minutes and C1 for ten minutes. Do not dispatch against this schedule.Logistics Kim; audio JeongLOAD-DRAFT-v3 / conflict marked 2026-11-08 15:10
Audio A01-R12026-11-09 08:40–09:20D2 08:45–09:05C1 08:55–09:15FOH installation now starts at 09:15. Confirmed that this does not affect the 11:00 rehearsal.Moved after the video team finishes using the route. The installation lead accepts the revised schedule.Venue Lee; audio Jeong; stage manager HanLOAD-v3 / 2026-11-08 16:00; driver acknowledges 16:20

Blank template preview

This preview shows a few rows. The downloaded file contains 24 prepared rows.

Eight columns · scroll horizontally to view the complete blank worksheet.

Loading-bay and Shared-route Schedule — blank worksheet
Supplier and task IDVehicle arrival and departureLoading bay and booking timesShared route and use timesInstallation position, sequence and start conditionsOverlapping times and changesVenue and supplier contactsApproved schedule version and change time
————————
————————
————————

Check your completed template

  • Clashes have been removed or an arrangement for controlling shared work has been approved.
  • The effect on installation and rehearsal has been checked.
  • Drivers and onsite teams have acknowledged the latest schedule.

What to pass to the next person

The logistics lead sends the current schedule to venue control, supplier crew chiefs and drivers.

Check before using this template

A schedule without overlapping times does not, by itself, prove that parallel work is safe.