Check that suppliers have quoted the same work, quantities and operating hours. Request prices for missing items, then separate amounts you can compare from those still awaiting a reply.

WHAT THIS TEMPLATE HELPS YOU PREPARE

A comparison showing why a supplier is recommended and which items need a revised quote.

File formats
English XLSX · CSV (UTF-8)
Version
2.0
Editorial review
24 Oct 2026
Use this for
Keep each original quote and check its lines against the common brief. Compare prices, quantities, tax, transport and operating work separately.

When to use it

Keep each original quote and check its lines against the common brief. Compare prices, quantities, tax, transport and operating work separately.

All example amounts are fictional prices before VAT, not market rates. Comparable totals do not replace contract approval or a selection decision.

Start with the guide: Event quote comparison: match scope, staffing and extra costs

Fill in the template step by step

When to use it

Use after receiving initial supplier quotes and before requesting purchase approval.

What to have ready

  • Common request sent to all suppliers
  • Original quotes and revisions
  • Operating hours, quantities and delivery conditions
  • Internal purchasing approval rules
  1. Match IDs for the same work before comparing whole-event totals.

  2. Mark missing tax, delivery, crew, backup and overtime conditions.

  3. Ask suppliers to requote excluded work on the same terms. Keep the version they return.

  4. Compare only amounts with matching conditions. Tell the approver what remains unanswered and why you recommend a supplier.

Worked example

Fictional example, not an actual event or supplier record

Eight columns · scroll horizontally to view the complete worked example.

Event Quote Comparison — Excel Template & Worked Examples — fictional worked example
Supplier and item IDConditions requested from everyoneEquipment and work quotedAmount and pricing unitIncluded, excluded or awaiting replyOriginal quote and versionDifferent conditions or reason to pausePerson to confirm, deadline and reply
A·AV01Display, delivery, install, six-hour operation, strike / RFQ04All requested work and a backup player includedKRW 4,800,000 / package / before VATNo additional cost awaiting confirmation; operation ends 18:00A-Q03-v2 / 2026-11-05 10:00KRW 4,800,000 for the common scope; ready to comparePurchasing lead Jeong checked the scope at 2026-11-05 17:00
B·AV01Same conditions as RFQ04Display KRW 3,900,000; delivery and operator excludedKRW 3,900,000 / package / before VATAwaiting confirmation of delivery KRW 350,000 and operator KRW 600,000B-Q08-v1 / 2026-11-05 11:00Do not rank on KRW 3,900,000 alone; request prices for both excluded itemsPurchasing lead Jeong requested a reply at 2026-11-05 17:00
B·AV01-R1Requested a revised quote including delivery, six-hour operation and backupDisplay 3,900,000 + delivery 350,000 + operator 600,000KRW 4,850,000 / common scope / before VATBackup confirmed; operation after 18:00 remains extraB-Q08-v2 / 2026-11-06 09:30KRW 50,000 above A; recommend A provided the same scope passes acceptance testsJeong submitted COMP-v2 at 2026-11-06 10:00; order approval still required
ILLUSTRATIVE AMOUNTS IN KRW

How missing costs changed the lowest quote

This additional fictional comparison uses a separate event scope and amounts from the record above.

Fictional figures for explanation only, not actual market rates, supplier quotes or delivered results. VAT at 10% is a calculation assumption; verify actual tax treatment separately.

A fictional one-day indoor event: setup 18:00–21:00 the previous day; rehearsal 09:00–10:00, show 10:00–18:00 and removal 18:00–20:00 on event day. Both suppliers were asked for the same equipment, two operators 08:00–20:00, return transport and removal.

Illustrative supplier scope and amount comparison
ComponentSupplier ASupplier B: initialSupplier B: revisedScope difference
Equipment and setup₩5,800,000₩5,600,000₩5,600,000Both quote the same equipment list and setup conditions
Operators₩1,200,000₩1,000,000₩1,200,000B initially: one person 09:00–18:00 → revised: two people 08:00–20:00
Return transport₩500,000Not quoted₩700,000B initially left this for negotiation → fictional reply confirms KRW 700,000
Removal₩500,000Not quoted₩800,000B initially excluded this → fictional reply confirms KRW 800,000
Subtotal excluding VAT₩8,000,000₩6,600,000 (incomplete)₩8,300,000Initial B omits unquoted costs.
Total including illustrative VAT₩8,800,000Comparison on hold₩9,130,000VAT assumption: 10%

Costs held out of the comparison

B left transport and removal out of the first quote and allowed different staffing hours. The buyer therefore paused the price ranking, left missing amounts blank instead of entering zero, and requested quotes on the same terms.

Request a revised quotation

Illustrative revised-quote request
Please send a revised quote against common request v1.1, including two operators 08:00–20:00, return transport and removal 18:00–20:00 on event day. Show the supply value, VAT and exclusions for each item. Please also state the unit used to charge for extra time. The assumed reply deadline is 15:00 on D−10.

Conditional extra costs

Do not add work beyond the agreed hours to the base price. This example assumes a separate quote of KRW 100,000 per hour excluding VAT for the two-person team, for up to two hours. The authorised approver must approve the extra work before it starts. It remains outside the base selection amount.

Reason for the final selection

In this example, the buyer selects A after both suppliers quote the same equipment, staffing, hours, transport and removal. A quotes KRW 8,000,000 before tax and B quotes KRW 8,300,000: A is KRW 300,000 lower. This illustrates a choice between fictional prices for the same work, not the quality or reliability of real suppliers.

Record the agreed scope

The selected scope is common request v1.1 and A quote v0.2. Copy the equipment list, two operators 08:00–20:00, setup/removal times, return transport and overtime approval conditions into the purchase order. Do not mark the order complete before approval.

Download English completed example

Blank template preview

This preview shows a few rows. The downloaded file contains 24 prepared rows.

Eight columns · scroll horizontally to view the complete blank worksheet.

Event Quote Comparison — Excel Template & Worked Examples — blank worksheet
Supplier and item IDConditions requested from everyoneEquipment and work quotedAmount and pricing unitIncluded, excluded or awaiting replyOriginal quote and versionDifferent conditions or reason to pausePerson to confirm, deadline and reply
————————
————————
————————

Check your completed template

  • Quantity, hours, work and tax basis match
  • Supplier replies support additional costs and exclusions
  • The recommendation and order approval are recorded separately

What to pass to the next person

Purchasing submits the original quotes, revised quotes and comparison to the budget approver.

Check before using this template

Do not select a lower-priced supplier automatically if delivery, rights or technical conditions remain unmet.

Sources used to develop this template

EVENTODIT created this template using the working methods described in the public sources below. It is not an official form and has not been reviewed or approved by those organisations.